SECTION
I
•SCOPE
1.1
ARCOR®
/ ARCOR®
coatings are high performance polymers designed for surface
protection in severe corrosive/erosive environments.
They have outstanding high temperature immersion
properties, good thermal shock and aging characteristics.
When applied to a metallic or nonmetallic surface, they act
as a complete barrier against corrosive chemical attack, fluid
particulate flow, low and high pH fluctuations and temperature
extremes.
1.2
A schedule for preparation and application should be devised to
insure the surface is prepared to the correct standards, then the
appropriate ARCOR®
/ ARCOR®
system applied before contamination or rust bloom occurs.
1.3
Appropriate personnel protective equipment should be utilized
during blasting of substrate containing potentially hazardous
material such as lead.
1.4
Although ARCOR®
/ ARCOR®
coatings do not contain solvent, adequate ventilation should be
provided for the work area. NIOSH respirator is recommended as a
precaution.
1.5
Application personnel should wear protective clothing - eye
shields, gloves and head garments to protect them for accidental
spillage and excessive skin contact.
1.6
Facilities should be provided to allow application personnel to
wash with warm soap and water to remove material BEFORE it cures.
1.7
Adequate lighting devices should be installed for all stages of
preparation, application and inspection.
1.8
If any staging or other structures are erected to facilitate
application, they should be inspected for safety prior to and
during their use.
1.9
Contractors/applicators should be familiar with the methods of
surface preparation and quality control recommended herein, and/or
be familiar with comparable information provided in SSPC, NACE or
ASTM reference material.
1.10
Prior to mixing and/or applying material, the
contractor/applicator should have read and understood this
Specification for Application and the appropriate ARCOR®
/ ARCOR®
technical data sheets, application sheets and material safety data
sheets.
SECTION
II
•
GENERAL INFORMATION
2.1
Instruction sheets briefly outlining the use of this product are
provided in every case/unit of material.
2.2
HANDLING AND STORAGE
2.2.1
Always keep material in original sealed containers until just
prior to use.
2.2.2
Store away from direct sunlight or flames.
Although this material is NOT flammable, it IS combustible.
Storage temperatures should be maintained between 55°F
(13°C)
and 95°F
(35°C).
Storage temperatures should be monitored and recorded.
2.2.3
Always keep material in a dry, clean environment.
To prevent accidental contamination by spent abrasive or
debris; this product should be kept away from the work area until
a clean up has been accomplished after surface preparation.
If accidental settling occurs, remove dust and debris from
lids prior to opening.
2.3
Thinning and Additives - never thin with solvents or use additives
in this product. The
addition of these ingredients could dramatically alter the cure
and performance of this product.
2.4
EFFECTS OF TEMPERATURE
2.4.1
This product is temperature dependent.
Cold temperatures (less then 55°F)
will cause a significant increase in viscosity (resistance to
flow). Therefore, the
material should be warmed by placing the sealed canisters in a
shallow pan of hot water, or gradually warmed by placing near a
heat outlet until the material temperature is between 65-78°F
(18-25°C).
A microwave oven can be used to heat the base component
material. A 1-kg base
unit can be heated on high for 45 seconds.
Increase or decrease time as conditions warrant.
Do not use a microwave to heat the activator component.
2.4.2
If the surface is cold, less then 65°F
(18°C),
this material will become stiff when applied, making it difficult
to evenly spread the material.
Warm the surface with a portable heater.
Never use kerosene, gasoline, oil or propane heaters, as
they will leave a residue on the substrate, which will hinder
adhesion. When
heating the substrate, pay close attention to dew point
calculations.
2.4.3
Hot temperatures (80ºF+) will lower the viscosity.
The higher the temperature the more difficult it will be to
apply normal thickness (15-30 mils) on vertical and overhead
areas. In such
situations, a second or even third coat may be required to obtain
desired film thickness.
2.4.4
Ideal temperature conditions for the ARCOR®
product, metal surface and ambient environment are 65°-78°F
(18°-25°C).
2.4.5
Cure of the product is also effected by temperature.
Lower temperature will increase the time required to cure.
Higher temperature will decrease the cure time.
This characteristic also effects pot-life or working time.
Consult material data sheets for pot life and cure
schedules.
*
Dispensing this material into shallow pans immediately after
mixing can extend Pot-life or working time.
SECTION
III
•
SURFACE PREPARATION
NOTE:
The importance of proper surface preparation should never be
understated. If
applied over an inadequately prepared surface, the optimum
performance properties of this ARCOR material will not be
achieved. Laboratory
studies convincingly illustrate that adhesion, heat resistance,
thermal shock, impact resistance and film integrity are all
reduced in direct correlation to the inferiority of the surface
preparation.
3.1
Remove grease, lubricants and oils.
Use a non-polar solvent, Acetone or MEK, which will not
leave a film (Isopropyl alcohol can be used in areas with solvent
use restrictions. Be
aware that larger volumes will be required and greater effort
applied.). Scrub with
wire wheel or brush. If
solvents are used to degrease the surface, rinse generously with
additional solvent after scrubbing.
QC
HOLD POINT:
Document surface cleanliness on
ARCOR® QC Inspection Report
3.2
Remove sharp edges and imperfections on the surface (e.g. weld
splatter). Grind
sharp edges to a minimum radius of 1/8” (approx.). Remove or grind down weld splatter until no sharp or abrupt
edges exist. Holes
and pits should be filled with a ARCOR®
rebuilding compound before coating the surface.
3.3
The air used for grit blasting must be free from contaminants,
such as oil and water. The
air supply should be equipped with oil and water filters.
Test purity of air by passing the air through a clean white
cloth for one minute at the beginning of each work period.
QC
HOLD POINT: Document
blast air cleanliness on ARCOR®
QC Inspection Report
3.4
Grit used for blasting and/or abrading must also be free from
contaminants especially chlorides. Verify cleanliness by placing a one pound representative
sample in a 5-gallon bucket of CLEAN water.
No oil slick or other form of contamination, except for
grit dust, should be visible on the water surface.
Chloride level can be tested with a Surface Contamination
Analysis Test Kit (SCAT). Copper
slag, Coal Slag (Black Beauty) or Aluminum Oxide abrasives may be
used to attain the desired level of cleanliness and surface
profile, subject to specific project requirements and limitations.
It may be acceptable to recycle the blast abrasive, taking
care to replenish with new material every two cycles.
Use a fine mesh screen to filter out debris.
For best results, limit recycles based on type of material
used.
QC
HOLD POINT:
Document abrasive cleanliness on
ARCOR® QC Inspection Report
3.5
Nozzle pressure should be 100-psi ± 5 psi.
Therefore, a typical system would be:
*
Compressor size - 375 cfm or greater
*
Compressor to pot hose size - 2-3” ID
*
Pot to nozzle size - 11/2-2” ID
*
Nozzle size - #5 or #6
3.6
Surface temperature must be maintained at a minimum of 5°F
(3°C)
above dew point during surface preparation and application of ARCOR®
materials.
QC
HOLD POINT:
Document surface temperature on
ARCOR® QC Inspection Report
QC
HOLD POINT:
Document dew point on
ARCOR® QC Inspection Report
3.7
Employ a dehumidification system during the blasting and
application stages. In
general, epoxies perform more predictably, and better overall
results are achieved, when the relative humidity is less than 60%.
The possibility of rust blooms is also reduced when
relative humidity is less than 60%. Use of a minimum 1,500-CFM desiccant-type dehumidifier should
maintain relative humidities at 40% or less.
QC
HOLD POINT:
Document relative humidity on
ARCOR® QC Inspection Report
3.8
Abrasive blast the entire surface to attain a scale free, oxide
free, metal finish with a minimum anchor profile of 3-5 mils and
SSPC rating in accordance with the Product Data Sheet.
Surface profile should be taken with Testex
‘X Course’ Press-O-Film tape.
Measurement of Tape profile is done with Testex Dial
Thickness Gage.
QC
HOLD POINT:
Document surface profile on
ARCOR® QC Inspection Report
3.9
Surface chloride contamination can drastically reduce the life of
a coating. Therefore,
it is necessary to test freshly blasted surfaces for chlorides and
ferrous ions (Fe) using a SCAT kit (see 3.5).
Chloride levels should be less than 50 PPM and Fe should be
less than 10 PPM. If
higher levels are found wet the entire contaminated substrate with
deionized or demineralized water to leach out the contaminants. Allow a minimum of 12 hours leach time. Re-blast the area and test again. If after two washes the desired contamination levels are not
attained, contact an ARCOR®
technical representative.
QC
HOLD POINT Document
SCAT results on ARCOR®
QC Inspection Report
SECTION
IV
•
IV.a. Weld
Stripe/Rebuilding & Primer Application
4.1
The ARCOR®
material should be applied as soon as possible after the surface
has been prepared. Continuous
use of Dehumidification to maintain less than 40% RH will minimize
potential oxidation of the substrate and should allow adequate
time (approximately 12 hours) for application of the prime coat.
If 12 hours is exceeded or if Dehumidification is not
maintained at less than 40% RH for the entire period or if
oxidation is visible as exhibited by a change in color of the
substrate, the entire surface should be re-blasted to clean off
the oxidation layer. This
cleaning blast will be less aggressive than the original blast
since profile has already been attained.
QC
HOLD POINT Document
relative humidity on ARCOR®
QC Inspection Report
4.2
If the surface becomes contaminated with oil, grease or lubricant
after blasting, wash thoroughly with non-polar solvent.
(See Section 3.1)
4.3
Be sure area is completely free from dust and spent abrasive.
After removing spent abrasive, allow particles to settle,
then blow down the surface with high pressure, clean and dry air.
Next vacuum the entire surface using a brush attachment to
insure all surface dust is removed.
The surface may then be solvent washed with a non-polar
solvent (MEK, Acetone) and allowed too completely dry.
Solvent wash is not required.
QC
HOLD POINT:
Document surface cleanliness on
ARCOR® QC Inspection Report
4.4
ARCOR®
recommends the application of ARCOR®
S-30 Prime as the first or prime coat. This product is specially formulated to flow into the pores
of the blast cleaned metal to effectively seal the metal from the
service environment and provide a good chemical bond to the chosen
ARCOR®
topcoat. For ferrous substrates, the addition of zinc phosphate
allows the S-30 Primer to resist corrosion undercutting when the
coating integrity has been breached.
QC
HOLD POINT Document
material batch # on ARCOR®
QC Inspection Report
4.5
The ARCOR®
coatings are two-component epoxies.
They are packaged in two canisters (Part A & Part B)
containing the proper mix ratio.
Add the entire contents of Part B canister into the entire
contents of Part A canister.
Consult the appropriate data sheets for mix ratios by
volume and weight. For
plural component spray application, insure that ratio settings
directly correspond to the volume ratio of the material being
applied.
4.6
Ambient and surface temperature should be at least 55°F.
Although the ARCOR®
products will cure down to 36°F,
application will be extremely difficult below 55°F
and curing will be very slow (See Section 2.4.2).
Surface temperature must be maintained at a minimum of 5°F
(3°C)
above dew point during surface preparation and application of ARCOR®
materials.
QC
HOLD POINT Document
surface temperature on ARCOR®
QC Inspection Report
QC
HOLD POINT Document
dew point on ARCOR®
QC Inspection Report
4.7
MIX COMPLETELY! Scrape side and bottom of mixing canister with wooden mixing
stick provided with each system.
Streaks indicate the material is not thoroughly blended and
further mixing is required. Mixing
time is normally five minutes.
A portable pneumatic or electric hand-held mixer may also
be used. A
“Jiffy-Mix” blade is recommended.
Avoid hitting sides and bottom of canister with blade.
This may introduce chips from the container into the
coating. After mixing
in original container material should be ‘boxed’ into a clean
container and mixed again for at least one minute.
QC
HOLD POINT Document
mix results on ARCOR®
QC Inspection Report
4.8
Consult Product Data Sheets for pot-life or working-time.
Dispense into smaller containers or paint trays to extend
working life. Higher temperatures will shorten the pot-life; lower
temperatures will extend pot-life (See Section 2.5).
QC
HOLD POINT Document
material applied within pot-life on ARCOR®
QC Inspection Report.
4.9
As appropriate, apply S-30 Prime to all weld areas, edges, seams,
joints and structural changes in the surface, by brush or roller.
Allow to set until dry to touch.
Stripe over the S-30 Prime with EE-92 using plastic
squeegee applicator. Smooth
material into surrounding substrate leaving no elevated edges or
uneven spots. Do not
apply beyond area coated with S-30 Prime.
Insure no skips, pinholes or voids occur in the coating.
4.10
Allow stripe coat to cure until dry to touch. Apply S-30 Prime
over entire surface with brush roller or sprayer.
Wet mil thickness should be a minimum of 20 mils.
Monitor film thickness with a wet-film thickness gauge.
Check every 10 square feet on open areas and every 5 square
feet near seams and structural changes in the surface.
All ARCOR®
coatings are “solvent free.”
This means wet film thickness will be the same as cured
film thickness. Consult
ARCOR® ‘Procedures For Spray Coating Application.
QC
HOLD POINT Document
wet-film on ARCOR
QC Inspection Report
•
IV.b. OVERCOATING
4.11
Apply second coat before first coat is fully cured.
Since temperature and humidity effect cure rate, the amount
of time required between coats will vary.
A sound bond will be accomplished between coats if the
guidelines in the Product Data Sheets are met.
The ‘fingernail’ test is commonly used to determine
whether the material is still within the overcoat window.
Press your fingernail into the coating.
If an imprint is easily made then the material is still
within the overcoat window. If
an imprint cannot be made, or can be made only with more than
moderate effort, it can be assumed the overcoat window has passed
and the material must be brush-blasted.
QC
HOLD POINT
Document overcoat window on ARCOR QC Inspection Report.
4.12
Should it be required to overcoat past the specified time
guidelines, the first coat must be brush-blasted to provide a good
bonding surface. It
is not necessary to allow additional cure before brush blasting
can begin. A
brush-blast should remove all material gloss and provide a profile
of 3-5 mils. If the
recommended overcoat time is exceeded by no more than 2 hours at
78ºF, brush blasting may not be required.
Although not generally recommended, the coating may be
wiped down with MEK (or similar Ketone solvent) to remove the high
gloss and provide good intercoat adhesion
(Follow cleanliness standards outlined in Sections 4.2 and
4.3). The solvent
wash method should not be used unless recommended by an ARCOR™
representative for a specific circumstance.
For
ARCOR®
S-30 Prime, S-30, EE-95, ARCTHANE the recommended overcoat
schedule is as follows;
• 55ºF 10-12 hours @ <60% RH;
• 65ºF 8-12
hours @ <60% RH;
• 75ºF 6-10
hours @ <60% RH;
• 85ºF 4-10
hours @ <60% RH;
• 95ºF 2-10
hours @ <60% RH.
4.13
Intercoat bonding is accomplished by a chemical reaction between
adjacent layers of coating which results in a monolithic coating.
Maximum adhesion is attained when the LEAST amount of time
passes between coats. Hence,
adhesion decreases as more time elapses between coats.
4.14
In general, overcoating should be accomplished as soon as the
previous coat ‘tacks up’, when it is no longer ‘wet’ to
touch. Normally
between 78ºF and 88ºF the product will tack up in 2 to 4 hours. The next layer should be installed as soon as possible, but
within 10 hours, at these higher temperatures, for best
performance. The
level of ‘tack-up’ depends on the application method being
used. By roller,
squeegee or brush ‘tack-up’ must be firmer than if spray
application is used. For
roller or squeegee a horizontal shear is applied which could
disturb the prior coat if it is not sufficiently tacked-up.
Use the thumb twist to determine if roller or squeegee can
be safely applied. Put
thumbprint onto coated surface and push and twist thumb with
modest pressure into coating. If coating is compressed wait one hour and try again.
When no compression is observed, coating may proceed.
QC
HOLD POINT Document
‘tack-up’ on ARCOR®
QC Inspection Report
4.15
Cure time increases sharply as temperature decreases.
It is important to remember that it is the temperature of
the substrate that will determine the coating temperature, hence
cure rate. At cooler
temperatures it may be necessary to add heat to accelerate the
cure to comply with scheduling requirements.
Between coats do not use kerosene, gasoline or any other
petroleum based heat source as they may deposit a film of residue
on the substrate or coating which will hinder adhesion or
intercoat bonding. Electric
heat sources are recommended.
Once all coating layers are applied it is acceptable to use
a petroleum based heat source (e.g. a torpedo heater) to
accelerate the full cure of the coating system.
When using added heat be very cautious of dew point,
humidity and overcoat windows.
QC
HOLD POINT Document
cure time & recoat window on ARCOR®
QC Inspection Report.
4.16
Spray apply additional coats of S-30 in accordance with section
4.5-5.15 until final film thickness is attained. Consult ARCOR®
‘Procedures For Spray Coating Application.
QC
HOLD POINT Document
wet-film thickness on ARCOR®
QC Inspection Report
SECTION
VI
•INSPECTION
6.1
Coating continuity must meet NACE Condition A, 100% pinhole free
coating system.
6.2
UV-QC (if applicable). After
application of S-30 Prime-UV, while still wet, the coated surface
is inspected using an ultraviolet light system.
All flaws and imperfections will show as a dark spot.
All spots are touched-up with a brush or squeegee using
fresh material.
After
application of a coat of S-30, while still wet, the coated surface
is again inspected using an ultraviolet light system.
All flaws and imperfections will show as a light,
luminescent spot. All
spots are touched-up with a brush or squeegee using fresh
material.
QC
HOLD POINT Document
coating continuity on ARCOR®
QC Inspection Report
6.3
The final coating should be allowed to cure a minimum of 12 hours
prior to DFT (dry-film thickness) measurements.
6.4
Coating thickness should be verified with a dry-film thickness
gauge. Measurements
should be made every 10 square feet on open areas and every 5
square feet around structural changes in the surface.
If readings less than the specified mil thickness are
observed, three additional readings over the 10 (or 5) square foot
area should be taken. If
three of the four readings are less than the minimum specified mil
thickness, the area should be identified with a chalk or marker
for repair. If less
than three measurements fall below the acceptance level, an
average is taken. If
the average is below the acceptance level the area is to be
identified with a chalk or marker for repair.
QC
HOLD POINT Document
dry-film thickness on ARCOR®
QC Inspection Report
6.5
The final coating should be allowed to cure a minimum of 24 hours
prior to high-voltage spark testing.
6.6
Visually inspect coating for skips, pinholes and other film
imperfections. Identify
flawed areas with chalk or marker.
It is preferred and recommended that holiday/pinhole
detection be performed with the aid of an electronic, high voltage
holiday detector using a minimum of 100 volts per mil of coating.
NACE currently recommends a voltage equal to 1000V times
the Ö
mil thickness. Spark testing can only be done on flat surfaces at
least 2” away from uncoated tube ends.
QC
HOLD POINT Document
spark test on ARCOR®
QC Inspection Report
SECTION
VII
•
REPAIRING IMPERFECTIONS AND FLAWS
7.1
If an imperfection has been detected within allowable overcoating
time (See Section 4.11), wipe the area with a solvent, allow to
dry and simply reapply a layer of ARCOR®
product. Be sure to
press the material firmly into the surface and feather edges.
7.2
If the material has cured, the area around the imperfection must
be roughened by grinding or grit blasting and solvent washed.
If the surface has begun to show signs of oxidation or rust
bloom, the surface must be thoroughly abraded back to clean oxide
free metal. It is not
necessary to wait until material has fully cured to begin abrading
the material. As with
the substrate, a 3 to 5 mil profile is recommended.
7.3
Should the measurements taken with the dry-film inspection gauge
prove to be below film thickness specifications, all these areas
should be brush-blasted (or solvent washed depending on overcoat
time).
7.4
After blasting or abrading, remove dust and spent abrasive from
the surface with a vacuum with brush attachment.
7.5
It is advisable, but not imperative, to wipe the abraded area with
solvent, allow to dry.
7.6
Apply according to Section IV.b.
Apply S-30 coating over abraded area with brush or
squeegee. Feather
coating into existing areas making sure not to apply coating over unabraided areas.
7.6
Inspect according to Section VI.
SECTION
VIII
•
CURE
Epoxy
coatings cure by a chemical reaction, which produces its own heat
(exotherm), causing the polymer to change from a liquid or
paste-like state into a hard, durable surfacing material.
Full cure or complete polymerization is generally
accomplished in 3 days at 72°F
(22°C).
8.1
Cure time, as stated in Section II, is dependent upon ambient
temperature and humidity. However, the following guideline will assist in determining
the extent to which the polymer has cured for exposure to certain
conditions at 75ºF.
Condition
Time elapsed after application
Light movement or stress
12 hours
Shipping
36 hours
Immersion or high loading
72 hours
8.2
Force curing or “baking” the polymer dramatically reduces the
amount of time required before the polymer can be stressed or put
into service. Between
coats do not use kerosene, gasoline or any other petroleum based
heat source as they may deposit a film of residue on the substrate
or coating which will hinder adhesion or intercoat bonding.
Electric heat sources are recommended.
Once all coating layers are applied it is acceptable to use
a petroleum based heat source (e.g. a torpedo heater) to
accelerate the full cure of the coating system.
When using added heat be very cautious of dew point,
humidity and overcoat windows.
8.3
Usually heat can be applied to the polymer before it has become
firm. However, care
must be exercised since applying heat to the polymer before it has
become firm may cause it to decrease in viscosity and slump down
the surface.
8.4
The addition of heat or force curing also enhances the chemical,
heat resistance and physical properties of the polymer.
8.5
For ARCOR®
S-30 Prime, S-30, EE-95, ARCTHANE the recommended force-cure
schedule is as follows;
• 90ºF (32ºC)
45 hours
• 95ºF (35ºC)
36 hours
•100ºF (38ºC)
27 hours
•105ºF (41ºC)
24 hours
•110ºF (43ºC)
20 hours
•115ºF (46ºC)
16 hours
•120ºF (49ºC)
12 hours
8.6
After force curing, always allow the coating to cool to ambient
conditions before subjecting it to high loading or service.
-END-